Summary

Unit A Biblis nuclear power plant in Hesse is operated by RWE Nuclear GmbH. Commercial operation began in 1975. Authorisation for power operation in accordance with the German Atomic Energy Act (AtG) expired on 6 August 2011. The first licence for decommissioning and dismantling was granted according to section 7 (3) AtG on 30 March 2017.

Details

General information

SiteBiblis
Federal stateHesse
Type (construction line)Pressurised water reactor
Current operatorRWE Nuclear GmbH
ManufacturerSiemens, KWU, Hochtief 
OwnerRWE Nuclear GmbH

Operational data

Application date12 June 1968
Start of constructionFollowing first partial licence of 31 July 1970
First criticality16 July 1974
First grid synchronisation25 August 1974
Start of commercial operation26 February 1975
Shutdown date18 March 2011
Expiry of authorisation for power operation in accordance with the German Atomic Energy Act (AtG)6 August 2011
First decommissioning and dismantling licence30 March 2017

Technical data

Thermal reactor power3.517 MW
Gross electric capacity1.225 MW
Net electric capacity1.167
Number of reactor coolant pumps4
Number of control elements69
Type of cooling systemRiver water cooling, forced draft wet cooling tower
All fuel removed from plantyes