Grohnde nuclear power plant (KWG)
Grohnde nuclear power plant (KWG) in Lower Saxony is operated by PreussenElektra GmbH. Commercial operation began in 1985.
Site | Emmerthal |
---|
Federal state | Lower Saxony |
---|
Type (construction line) | Pressurised water reactor (pre-Convoy) |
---|
Current operator | PreussenElektra GmbH |
---|
Manufacturer | KWU |
---|
Owner | PreussenElektra GmbH, Stadtwerke Bielefeld |
---|
Application date | 3 December 1973 |
Start of construction | 9 June 1976 |
First criticality | 1 September 1984 |
First grid synchronisation | 5 September 1984 |
Start of commercial operation | 1 February 1985 |
Expiry of authorisation for power operation in accordance with the German Atomic Energy Act (AtG) | 31 December 2021 |
First decommissioning and dismanting licence | 6 December 2023 |
Thermal reactor power | 3,900 MW |
---|
Gross electric capacity | 1,430 MW |
---|
Net electric capacity | 1,360 MW |
---|
Number of reactor coolant pumps | 4 |
---|
Number and mass of fuel elements in the reactor core | 193, mass per fuel element 850 kg |
---|
Number of fuel rods per fuel element | 236 |
---|
Composition of the nuclear fuel | 1.9 - 4 w/o U-235 (uranium oxide with 1.9 - 4 % U-235) |
---|
Type of cooling system | 61 |
---|
Kühlungsart | Natural draft wet cooling tower |
---|