Unit 3 Greifswald nuclear power plant

Summary
Decommissioning of Unit 3 Greifswald nuclear power plant (KGR 3) in Mecklenburg-Western Pomerania is being carried out by EWN Entsorgungswerk für Nuklearanlagen GmbH. Commercial operation began in 1978. The plant was shut down on 28 February 1990.
Details
General information
Site | Rubenow |
---|---|
Federal state | Mecklenburg-Western Pomerania |
Type (construction line) | Pressurised water reactor (WWER-440/213) |
Current operator | EWN Entsorgungswerk für Nuklearanlagen GmbH |
Operator prior to decommissioning | VE Kombinat Kernkraftwerke "Bruno Leuschner" |
Manufacturer | VEB Kombinat Kraftwerksanlagenbau |
Owner | EWN Entsorgungswerk für Nuklearanlagen GmbH |
Operational data
Application date | 25 May 1967 |
---|---|
Start of construction | October 1972 |
First criticality | 6 October 1977 |
First grid synchronisation | 3 November 1977 |
Start of commercial operation | 6 May 1978 |
Shutdown date | 28 February 1990 |
Technical data
Net electric capacity | 408 MW |
---|---|
All fuel removed from plant | Yes |
Number of control elements | 193 |
Documentation
Authority | Ministry of the Interior and Europe of Mecklenberg-Western Pommerania Department II 2 Arsenal am Pfaffenteich Alexandrinenstrasse 1 19055 Schwerin |
---|