Unit 5 Greifswald nuclear power plant
Decommissioning of Unit 5 Greifswald nuclear power plant (KGR 5) in Mecklenburg-Vorpommern is being carried out by EWN Entsorgungswerk für Nuklearanlagen GmbH. Trial operation began in April 1980. The plant was shut down on 29 November 1989.
| Site | Rubenow |
| Federal state | Mecklenburg-Vorpommern |
| Type (construction line) | Pressurised water reactor (WWER-440/213) |
| Current operator | EWN Entsorgungswerk für Nuklearanlagen GmbH |
| Operator prior to decommissioning | VE Kombinat Kernkraftwerke "Bruno Leuschner" |
| Manufacturer | VEB Kombinat Kraftwerksanlagenbau |
| Owner | EWN Entsorgungswerk für Nuklearanlagen GmbH |
| Application date | 4 March 1977 |
|---|
| Start of construction | July 1977 |
|---|
| First criticality | 26 March 1989 |
|---|
| First grid synchronisation | 24 April 1989 |
|---|
| Shutdown date | 29 November 1989 |
|---|
| Net electric capacity | 408 MW |
|---|
| All fuel removed from plant | Yes |
|---|
| Number of control elements | 193 |
|---|
| Authority | Ministry of the Interior and Europe of Mecklenberg-Vorpommern Department II 2 Arsenal am Pfaffenteich Alexandrinenstrasse 1 19055 Schwerin |